Networks in Practice - StudyPulse
Boost Your VCE Scores Today with StudyPulse
8000+ Questions AI Tutor Help
Home Subjects General Mathematics Networks in practice

Networks in Practice

General Mathematics
StudyPulse

Networks in Practice

General Mathematics
01 May 2026

Using Networks to Model and Solve Practical Problems

Why Networks?

Many real-world problems involve connections, routes, and resource flows. Network models make these problems visual and tractable. General Mathematics focuses on applying network algorithms to genuine scenarios.

Common Practical Applications

Context Network model Algorithm
Road navigation Weighted directed graph Shortest path (Dijkstra)
Utility infrastructure Undirected weighted graph Minimal spanning tree
Project planning Activity-on-edge diagram Critical path analysis
Delivery routing Complete weighted graph Hamiltonian circuit
Cable/pipe layout Undirected graph Minimal spanning tree
Traffic flow Directed graph with capacities Maximum flow

Worked Example — Infrastructure Planning

A telecommunications company needs to lay fibre cable connecting 5 suburbs (A, B, C, D, E). The cost (\$ thousands) of connecting each pair:

Route Cost
A–B 8
A–C 5
B–D 6
C–D 3
C–E 7
D–E 4

Find the minimum cost to connect all suburbs (MST):

Sort by cost: C–D=3, D–E=4, A–C=5, B–D=6, C–E=7, A–B=8.

Apply Kruskal’s: Add C–D, Add D–E, Add A–C, Add B–D. Now all 5 vertices connected with 4 edges.

MST cost = 3+4+5+6 = \$18,000.

Worked Example — Project Scheduling

A building project has activities with durations (days):

Activity Predecessors Duration
A 3
B 5
C A 4
D B 2
E C, D 6

Draw the network, find EST and LST at each vertex.

Critical path: B → D → E (5+2+6=13 days) is the longest path, so minimum project duration = 13 days.

Activities A and C have float (can be delayed without affecting completion).

Interpreting Results in Context

Always express answers in the units of the problem:
- “The minimum time to complete the project is 13 days.”
- “The minimum cable cost is \$18,000.”
- “The shortest route from depot to delivery point is 6 km, via C and D.”

VCAA FOCUS: VCAA assessment emphasises interpretation. A correct algorithm answer that is not interpreted in context (units, meaning) will not receive full marks.

STUDY HINT: Practise drawing network diagrams neatly and labelling all edges. Messy diagrams lead to missed edges and algorithmic errors under exam conditions.

Table of Contents